Which permits cover irrigation diversions?

Water right, structure and stream permits

BOISE, Idaho — An irrigation diversion usually involves up to four kinds of permission: a water right that says you may take the water, a state permit for the diversion structure or headgate, a stream or floodplain permit for work in or near the channel, and sometimes a federal permit when the work affects wetlands or navigable waters. Which of these apply to you depends on the state, the water source and what you're building. Most farmers only deal with some of them, but you need to know which.

The water right

This is the foundation. In western states, your right to divert is tied to a priority date, a source, a place of use, an amount and a purpose. A diversion without a right behind it is a problem no matter how well built. If you're buying or leasing land, ask for the water right documents and have the state water agency confirm that the right is valid, and that the place of use and point of diversion on paper match what's on the ground. In riparian states the rules are different, and many require a withdrawal permit above certain volumes. Your state water agency is the source of truth.

The diversion structure

A headgate, check dam, pump intake or push-up dam in a stream can need its own approval. Many states review structures for safety and stream impact. A temporary push-up dam bladed up every spring has caught plenty of farmers off guard, because the repeated work in the channel can trigger fish and wildlife or stream alteration permits. Ask the state environment or natural resources agency whether your work counts as a stream alteration and whether it can only happen during certain windows of the year.

Federal and local layers

Work that places fill in wetlands or streams may need a Section 404 permit from the Army Corps of Engineers, and the state may also issue a certification. Floodplain work can require a county permit. Irrigation districts and ditch companies sometimes add their own approval for anything touching their canal or turnout. If you take part in USDA programs, your local FSA or NRCS office can tell you whether wetland compliance is part of the picture. The farmers.gov conservation page is a decent starting place for program options.

Pumping from a stream or canal

Pumping isn't exempt from the right requirement. Ask whether you need a pump permit, meter or screen on the intake. Fish screens are common requirements in some states, and they protect both fish and your pump. Ask how much you may pump, over what season, and whether you have to stop when senior users aren't getting their water.

A way to sort it out

  1. Pull your water right and confirm the amount, place of use and point of diversion.
  2. Call the state water agency about any structure or change.
  3. Call the state fish and wildlife or environment office about stream work.
  4. Ask the Army Corps district about wetlands or waters.
  5. Check with the county about floodplain rules and with your ditch company about its policies.

Keep the record

File each approval, plus photographs of the headgate before and after any work. When you change a point of diversion or place of use, most states require a formal change approval. Doing the work first and asking afterward is a gamble, and a watermaster with a ledger is not a patient gambler.