How do I size a manure storage facility?
Start with days, not gallons
TULARE, California — Sizing manure storage starts with a question about calendar days, not tank dimensions: how many days can't you spread, and how much material will you make in that time? Your answer plus a margin for rain and freeboard gives the working volume. The final design, though, should come from an engineer or NRCS planner who knows your state standards.
Here is the logic they follow, so you can check the numbers and ask better questions.
Decide the required storage period
Storage period is the longest stretch you can't legally or agronomically apply. That depends on climate, crop calendar, soil, and state rules. A farm with a short growing season and frozen ground for months needs more days than one that can spread nearly year-round. Many state programs set a minimum number of days, so look up yours through your state agriculture department or NRCS office. Don't guess from the neighbor's pit; the neighbor may have fewer cows or a looser plan.
Add up the daily inputs
List everything that enters the structure:
- Manure and urine from each animal group that uses the barn
- Wash water from the parlor, holding area and milkhouse
- Bedding or feed refusals that get scraped in
- Precipitation falling on the storage surface and any roofed-off or open lots draining to it
- Runoff from the area that drains to the pit
Multiply the daily total by the storage period. This is where most undersized pits go wrong: the cow part was counted, the water and rain were not.
Account for the design storm and freeboard
Open lagoons and basins need room for the rainfall allowance your state requires for a wet stretch, plus freeboard, the empty space between the top of the liquid and the lip. Freeboard isn't spare capacity; it's the margin that keeps an overflow from happening. Agencies set minimums, so ask your planner which ones apply. Also leave space for solids that settle and never get pumped out.
Think about growth and the pumping plan
If you plan to add cows in a few years, size for that herd now, or design an expansion path. Retrofits cost more than adding capacity during the first build. Also consider how you'll empty the structure: agitation, pump access, a ramp, and a spreader that can keep up. A pit that holds six months of manure is of little use if you only have two days a year when the weather lets you pump it.
Check the permits and get it designed
Large operations may need a permit under federal or state rules, and the design usually has to meet a recognized standard. Contact your state agency and local NRCS service center before you pour anything. Ask what soil investigation is needed. The Web Soil Survey gives a first look at soils and depth to water table, though a site investigation will still be required for liners and foundations.
Questions to bring to the first meeting:
- How many days of storage does our state require?
- Which rainfall allowance and freeboard apply here?
- What liner or concrete standard fits our soils?
- Is cost-share available, and what does it need before construction begins?
Don't start digging before the paperwork is done. Cost-share programs often won't pay for work started early, and a half-built pit is an expensive hole.